Takt time calculator
Find the takt time, the pace your line must follow to meet customer demand.
How it is calculated
Takt time = available time ÷ customer demand.
Worked example
460 min available, 115 units demanded: 460 ÷ 115 = 4 min per unit (240 s).
Steps
- Subtract breaks and planned stops from shift time.
- Enter the demand for the same period.
- Use the result as the target cycle time.
Frequently asked questions
Is takt the same as cycle time?
No. Takt is the pace demand requires; cycle time is what the process actually takes.
Should I include overtime?
Only if overtime is planned and regular.
What if demand changes?
Recalculate takt for each planning period.
References
Takt definition from Lean Production (Womack and Jones) and Toyota Production System practice.
Estimates for information only. Verify critical values with a qualified engineer or your supplier standards.